Good progress on new retaining walls.
Camex Civil is on the job in Wily Terrace following the interruption caused by Alert Levels 3 and 4. The work to stabilize the roadway, footpaths and adjacent slopes in Wily Terrace and Acacia Bay Road is being carried out to provide a long-term solution to slips that have occurred in the area and has a budget of $1 million.
Project involves construction of six retaining walls including three timber cribs walls, two steel post walls and one MSE Duramesh retaining wall in Acacia Bay Road and Willy Terrace alongside Lake Taupo.
The first Timber Crib Wall has just been completed and the client is happy with the progress as we move through the project.